Posts

Construction Scheduling. Schedule Performance Measurement, Part 3. (For Owners).

When monitoring and responding to the Contractor’s schedule performance on the project, how do you know if the schedule update is even valid for use?

When we review a schedule progress update, we need to first determine if the schedule update is a valid update. By that, I mean is the logic still complete? Have there been any revisions with this update that result in the schedule not meeting the contract requirements or best practices? It doesn’t take much to render a schedule useless….

There are most likely logic revisions, changes to lag values, or possible changes to calendars or assignments. There are also deletions and additions of activities and/or Activity Relationships. Then there are changes to quantities or Resources which may impact Activity Durations or Resource Calendars.

For this post, we will address changes to Relationship Lags.

Personally, the first schedule “quality check” I make is for complete logic. Please see the previous post, Schedule Performance Measurement, Part 2. (For Owners).

One of the things that are really hard to check, using Primavera P6, is changes to Activity Relationship Lags.

Often, when the Contractor is making schedule revisions to recover lost time for the update period, they make subtle changes to logic. They also make changes to the Relationship Lag values assigned to specific Activity Relationships. If they have modeled the sequence of work using SS Relationships with Lags, they may reduce the Lag value for an activity, driven by the Activity Relationship with the Lag, to gain a day or so. If there is an FS Relationship with a Lag, they may reduce that lag value as well.

They can also change the Relationship Lag’s effect by changing the Activity Calendar of the Activity selected to determine the Relationship Lag’s behavior.

None of this is easy to check in Primavera P6 and is not readily transparent in a Gantt Chart.

Most of us use third-party software designed to identify changes to Relationships and Relationship Lags. That’s great, but we still need to understand the impact of the changes identified.

Changes to Relationship Lag values does not make the schedule invalid for use. But, the owner needs to know what changes were made and what effect the changes have on the affected Logic Path. Some specifications prohibit the use of Relationship Lags. Many specifications allow limited use and do not allow the use of negative Lags at all. I prefer to minimize the use of Lags and do not like to use Negative Lags. There are conditions which warrant the use of a Negative Lag, but the condition has to be monitored and other options for modeling the work sequence should be exhausted.

That said, finding the changes to Relationship Lags, understanding the impact of the changes found, and reporting those findings is important to the Owner.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what the performance of the actual work in the field is, compared to the planned performance. Unless we have a valid schedule update to measure with, and against, and understand the impact of acceptable schedule revisions, we cannot provide an accurate measurement.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Schedule Performance Measurement, Part 2. (For Owners).

When monitoring and responding to the Contractor’s schedule performance on the project, how do you know if the schedule update is even valid for use?

When we review a schedule progress update, we need to first determine if the schedule update is a valid update. By that, I mean is the logic still complete? Have there been any revisions with this update that result in the schedule not meeting the contract requirements or best practices? It doesn’t take much to render a schedule useless….

There are most likely logic revisions, changes to lag values, or possible changes to calendars or assignments. There are also deletions and additions of activities and/or Activity Relationships. Then there are changes to quantities or Resources which may impact Activity Durations or Resource Calendars.

For this post, we will address changes to the logic.

Personally, the first schedule “quality check” I make is for complete logic. The Primavera P6 schedule log provides a basic check. But I also use third party software that provides a more in-depth check for activities which may only have an SS relationship to their only successor activity. Sometimes, the check uncovers missing lag values or “reverse logic”. It may even uncover an SF relationship. All of these must be identified and addressed.

Often, when the Contractor is making schedule revisions to recover lost time for the update period, they make subtle changes to logic. As a Project Owner or CMa, we need to understand what was revised and why. If the relationship for an activity in the current or previous period Longest Path was changed from an FS relationship to an SS relationship, with or without a lag, to pull the scheduled Finish Date back, we need to understand that.

The same applies to the previous period or current update Near Critical Path(s).

If the contractor makes a logic revision for an activity which results in the only successor activity having an SS relationship, an open end is created. (There should have been an FS or FF relationship added to complete the logic). Otherwise, the finish of the activity does not drive anything in the schedule. This is an open end, (which does not show up on the Primavera P6 schedule log).

Any “open end” relationships make the schedule network logic incomplete. Sure, there are activities that once complete will not drive any other activity or work until the project is complete, if that is the case, they should be tied to Final Completion or whatever the last activity in the schedule is called. But more likely, the activity relationship was missed during development or when making revisions.

However, if this activity is supposed to drive other work, the relationships should model this. Not having complete logic for just one activity results in an erroneous schedule network. The activity could potentially be Critical or Near-Critical, but without the complete logic, there is nothing in the schedule to model the intended sequencing of the work for the affected network path. This means the Total Float values and scheduled dates for driven successor activities on this logic path are incorrect.

One of the basic checks and the first check I make is to verify the schedule network logic is complete. As an owner’s rep, we cannot know the detailed intent of the schedule sequencing, but we can identify open ends and any questionable logic we discover.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what the performance of the actual work in the field is, compared to the planned performance. Unless we have a valid schedule update to measure with, and against, and understand the impact of acceptable schedule revisions, we cannot provide an accurate measurement.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Schedule Performance Measurement, Part 1. (For Owners).

Are you responsible for monitoring and responding to the Contractor’s schedule performance on the project?

Do you review each schedule update and compare dates in the new update with the dates in the baseline schedule?

Do you compare the Milestone Activity dates to the baseline schedule?

There are many different methods of analyzing project schedule performance.

When we review a schedule progress update, we need to first determine if the schedule update is a valid update. By that, I mean is the logic still complete? Have there been any revisions with this update that result in the schedule not meeting the contract requirements or best practices? It doesn’t take much to render a schedule useless….

There are most likely logic revisions, changes to lag values, or possible changes to calendars or calendar assignments. There are also deletions and additions of activities and/or Activity Relationships. Then there are changes to quantities or Resources which may impact Activity Durations or Resource Calendars, depending on the schedule settings selected.

This should all be addressed in a manner that conveys the actual revisions with the reasons for the revisions as part of the schedule update narrative the Contractor submits with the schedule update. Unfortunately, this is rare. Typically, we see the “digger” report with a general comment addressing the high-level view of the update.

Not really helpful for our use.

So, we plow ahead with the intent to complete our review of the schedule update for this period.

First, we need to complete several “quality checks” of the schedule to validate it for use.

In my next post, I will walk through some of the more common items we check for.

Until then, be suspect of schedule updates without, or with vague schedule update narratives. There is much that can be changed in the program, that will not be transparent to the owner without a thorough review and analysis of the file by an experienced schedule professional.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what the performance of the actual work in the field is, compared to the planned performance. Unless we have a valid schedule update to measure with, and against, and understand the impact of acceptable schedule revisions, we cannot provide any accurate performance measurement.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Is the Schedule a Complete Schedule? (For Owners).

Do you review your Baseline Schedule to make sure all the work to complete “The Project” is included?

Are you sure?

When the contractor develops the schedule, they should be planning the project execution first. This includes the phasing of the project, the necessary permits, the long lead submittals, the procurement of subcontractors, equipment, and material, the close-out of the project, and the actual work necessary to build the project.

Often, we see schedules which do not include permits, or the procurement of long lead items, or complete commissioning, testing, and inspections. Let’s not forget the closeout requirements for as-built documents, warranties, or training, (if required).

The CPM schedule should include all the work necessary to execute the project.  An easy way to ensure all the work is included is to make a list of all the closeout deliverables and compare that to the WBS for closeout section of the schedule. The same for special inspections, commissioning. For whatever reason, we always look closely at the construction section of the schedule, but tend to gloss over the administrative, procurement, and commissioning sections.

Just as we look at constructability for the project plans, we need to thoroughly look at the project schedule to make sure all of the deliverables are included. And, the activities to provide these deliverables need to be complete and broken down into sufficient detail to control the work!

An activity at the end of the project schedule that says “Finish Project” is of no use. All the activities necessary to actually plan and control the post “Substantial Completion” work for the project should be as detailed as the construction work is. The same for the commissioning and testing of systems.

And, let’s not forget the initial administrative requirements which have to be fulfilled prior to starting any work. We usually need an approved Safety Plan, an approved environmental permit, and building permit at a minimum. The time to develop these, get them submitted and reviewed and approved needs to be in the front of the schedule.

Also, we need the long lead time equipment or material submittals in the schedule. I also like to have the main materials submittals, in general form, in the schedule just to make sure we get them in and reviewed in time for their use in the project. Often, the contract documents state the required review period for the owner. We use this for the review period in the schedule.

There should be a fabrication and delivery activity(s) for any major equipment which should drive the start of any installation of the equipment. This activity(s) should be driven by the submittal and procurement of the equipment. Often, this will drive the Critical path.

Everyone tends to really look at the construction activities. As  Planning and Schedule Professionals, we need to look at the project deliverable as a whole.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. What Schedule Reports do you Need? (For Owners).

Do you receive a truckload of schedule reports each month from the contractor?

Do you actually look at or use them all?

Do you know there are many ways of looking at the schedule to be able to review progress, planned work, work that is slipping, or work that is Near Critical?

There are all kinds of reports the contractor can provide. But, it’s best if they know what you will need before they develop the Baseline Project Schedule.

When the contractor develops the schedule, they create groups of activity codes which they assign to activities to be able to filter, sort, and group activities in various ways.

They can assign phase, trade or responsibility, area, work type and many other code assignments.

The CPM schedule can be presented is a number of ways, but typically, we see an xer file, a schedule narrative, and a group of “layouts” in pdf format.

As the owner, you need to know what “layouts” to ask for!

Your specifications should at a minimum require a Critical Path layout with the Critical Path set to equal the Longest Path. I like to show the activity ID, Description, Physical and Duration Complete, Original, Remaining and AT Completion duration columns. Also, the Start, Finish, and Total Float columns. I like to group this by the project and sort on Start and then Finish Dates. This provides the “waterfall” view of the Critical Path. With the At Completion Duration column shown, I can see if there is any delay to any in-progress activities driving the Critical Path.

Your specifications should also at a minimum require a Total Float layout. I like to set this up to be grouped by the project, sorted on Total Float and then Start and then Finish. I show the same columns as I do for the Critical Path layout above. This provides a series of “waterfalls” based on Total Float values. For projects with multiple activity calendars, we cannot rely on the Total Float value to provide an accurate representation of the Near Critical Path(s) and subsequent network paths. But, it is very useful if you keep in mind what activity calendar the types of activities you are looking at typically have assigned. Knowing another network path is only a few days away from being Critical is, well, critical.

The classic layout grouped by WBS or some sort of activity coding is typical. This is the layout you get which shows the project phasing and deliverables broken down with the supporting activities. This is a necessary layout and is almost always provided by the contractor.

There are ways to format a layout to show activities taking longer than planned, not starting or finishing as planned, and planned to start or be underway in the next few weeks. These layouts are all helpful to the owner and the contractor.

Feel free to ask me about layouts I typically use. I’m happy to explain what I use and why.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what presentations to require. We can help them.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. The Reality of a Project Schedule, (For Owners).

Do contractors and project owners view the project schedule differently?

Most of the time? You bet!

The contractor develops the schedule because the contract specifications require a project schedule or because they need a plan to manage the project execution or both. Does the contractor need the same degree of detail or planning as the project owner? Probably more.

The project owner wants the project schedule as assurance from the contractor that they have a plan and can execute the project. They also need the schedule to plan their own activities for the project and plan internal activities which may be separate from the project.

Most projects now require a CPM schedule. This forces the contractor to develop more detailed logic, with specific calendars. They cannot get by with a simple bar (Gantt) chart type of a schedule which simply lists the activities in the planned sequence. The contractor must develop a complex organization of finite activities with associated logic, calendars, constraints and best practices.

The project owner benefits from this, they can have a higher level of confidence in the schedule!

Or can they?

When you plan the project by breaking down the deliverables, verifying resources availability, acknowledging internal and external constraints, and planning the basic phasing and sequencing if the work, the required project completion date is a facet of the planning, but not the driver. We simply plan how we will schedule the project.

When we sequence the deliverables and add the supporting activities, based on our planning effort, we often find we will not finish the project by the contract completion date, as required.

We then consider adding resources to shorten activity durations and/or sequencing some work to run concurrently. We do this by attacking the current Longest Path, iteratively as the Longest Path keeps shifting until we have a schedule that meets the contract completion requirements.

As the project owner, you generally do not know about this exercise. You do not realize how much schedule risk has been added to the project. For larger and more sophisticated projects or owners, the use of risk management for cost, scope, and schedule is common. But, for many medium and some larger projects, there are not resources available for risk assessment and management.

For these projects, the owner believes the contractor can execute the project as planned. Often, the contractor is anxious and understands there is the additional risk and has analyzed the risk and provided a mitigation plan. However, the risk remains.

Any impact to the project schedule Critical or Near Critical Path can derail the project. There simply isn’t schedule contingency available to absorb any impact. Many owners believe the contractor has built-in contingency, just as they believe the contractor has a cost contingency. Usually, they have a cost contingency, but often it is negligible. They bid the project to win the project and keeping the contingency slim is part of winning….

Seldom is there any real schedule contingency. Contractors must address even slight impacts to the execution or sequencing of work. Owners believe the contractor should anticipate these and absorb them. It is all contractors can do to mitigate their own impact issues, much less absorb owner impacts.

How can we, as Planning and Schedule Professionals help?

I can only speak for myself…

When providing owner’s schedule oversight and management support, I try to identify the types of items in the schedule which would prevent the project team from using the schedule to accurately forecast and manage the work. It is in the best interest of all parties if the schedule is valid for use. Often, the contractors disagree and push back, but for the benefit of the project as a whole, we have to force the use of solid, valid CPM schedules.

Unfortunately, and far too often, the contract schedule requirements do not provide the support necessary to force the quality of schedule we need…. So, we do the best we can…

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. “All the Other Work” Progress Update Information for Owners.

As a continuation of my previous posts, I will continue to discuss some of the important progress update items we review and analyze.

I will now discuss the process of analyzing the actual performance of work NOT on the Critical and Near Critical Path(s).

When the contractor adds the actual Start and Finish Date and expected Finish Date data to the schedule update, the new scheduled completion date if most often not what any of us want. Usually, there has been slippage in work progress in an area that must be addressed.

This is most often caused by a lack of adequate progress for work on the Critical Path and/or the Near Critical Path(s).

However, we must not forget to monitor and address non-performance for work not on the Critical Path or Near Critical Path(s).

One of the reasons we work to make the schedule logic as complete and defined as possible is to allow the planned sequencing of finite work activities to drive the schedule. This provides a dynamic logic network for the planning and control of the project.

The result of all the work breakdown, resource allocation, and logic assignments produces multiple network “paths” through the schedule. The paths we’re always looking for is the Critical Path, and then the Near Critical Path(s). These are determined by the scheduling algorithm and have Total Float values based on this calculation.

But what about the “other” activities that are not Critical or Near Critical? They have higher Total Float values, so they can be done anytime as long as we don’t let them get Critical, right?

That is not a good idea. I believe it is best to complete the work, when you can; efficiently, of course. Letting the work push out because it is not “Critical” or has “Float” only sets the project up for failure.

If you’re cost or unit loading the schedule, you typically produce a Baseline Curve of some sort to plot the resource or cost spread over time. This curve is comprised of all the activities. Letting work slip pushes the curve and the required cost and resources out and this can quickly overwhelm the availability of resources to complete the work when it “stacks” up. Unfortunately, this is all too common.

Many Superintendents push their work everywhere, all the time, and for good reason. They learned early on that letting work slip will come back to haunt them.

The owner needs to monitor for work slippage. The project can easily show an on-time completion with the Critical Path looking very pretty. But, they should also be concerned with the Schedule Performance Indicator. This will show if work is pushing out because the projected curve will push out. Of course, we have to balance the work, so we maintain the curve and the Critical Path to achieve on-time completion, in the most cost-effective manner. This is another item the Owner’s scheduler should be analyzing and reporting on. We can list activities which did not start as planned, did not finish as planned or could have started but did not. We can also list activities which have started but made little or no progress. While there are going to be valid reasons for some work not starting, finishing or progressing as planned, the reasons should all be explained in the schedule update narrative provided by the contractor. They know the reasons and can best explain them. If they do not provide this information, the project team really needs to investigate and determine what is driving the slippage. It is much better to tackle this kind of problem early. It is rare that a project can recover if slippage continues very long at all.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Critical and Near Critical Progress Update Information for Owners.

As a continuation of my previous posts, I will continue to discuss some of the important progress update items we review and analyze.

I will now discuss the process of analyzing the actual performance of work on the Critical and Near Critical Path(s).

When the contractor adds the actual Start and Finish Date and expected Finish Date data to the schedule update, the new scheduled completion date if most often not what any of us want. Usually, there has been slippage in work progress in an area that must be addressed.

This is most often caused by a lack of adequate progress for work on the Critical Path and/or the Near Critical Path(s).

Quite simply, the planned productivity for the work scheduled is not achieved.

To analyze this, we compare the previous period update Critical Path work to the actual progress reported in the current period update schedule. We simply compare Original Duration and scheduled dates to the actuals. This tells us where the slippage occurred. It does not explain the why. This should be included in the schedule update narrative the contractor provides.

We do the same for the Near Critical Path(s).

Why do we do this?.

The contractor typically knows what is driving the project and what measures need to be taken to correct work slippage. The owner usually does not have this intimate knowledge of the background operations of the contractor. However, the owner is entitled to know as much as possible about the actual and planned performance of the project. They need that information to make internal business decisions which may impact the project, such as potential change orders and work integration by others, or to react to deviations from the planned contract milestone dates.

More importantly, to me anyway, the owner is always in a position to help the contractor and I’ve met very few owners who would not do so if they understand the problem and are in a position to do so.

Once we identify and quantify the lack of progress, we can determine the root cause and identify a trend, if one is developing. We cannot do this if we simply look at another Gantt Chart pdf and look at the scheduled finish date for the project.

The owner needs to understand what work is slipping and why and this should be discussed with all parties to find a solution to keep the project safe. But this does not happen if the owner is not fully informed of progress slippage for Critical and Near-Critical work.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Actual Date(s) Progress Update Information for Owners.

In my previous post, I touched on some of the important progress update items we review and analyze.

I will now discuss the process for Actual Start and Finish Dates and partial progress of work in progress. I will not hit this too hard as most everyone understands this process and the process varies from industry to industry. But the basics are very similar.

When the project is large, or smaller, and there is a full-time Owner’s Scheduler on the project, the Owner’s scheduler can periodically walk the project with various team members to validate Actual Start and Finish Dates. More often, for me as a Schedule Consultant, I rely on that verification by the Owner’s Representative on site. It’s a standard part of developing the “pencil copy” pay application or draft invoice.

However, what often happens is the review is overly concerned with determining what percent complete work in progress is. While this is important, getting the accurate Actual Start and Finish Dates is critical as well.

When working with the contractor to determine the progress for a performance period, we typically walk the project and either agree or disagree with their assessment. We should also be reviewing our daily reports for the actual dates.

Back when I was an inspector, I liked to keep a copy of the three week look ahead schedule with me so I could jot down an actual date when I came across it in the field. This allowed me to write it and forget it so I could focus on other matters. It was also very helpful when reviewing the “pencil copy” pay application.

Coming to the agreement of percent complete for work in progress was not too difficult, but getting the expected Finish Date was. We really had to discuss the performance of that work individually, decide if the progress was improving, had some delay or was simply not important enough today to throw resources at. In any event, the expected Finish Date for an in-progress activity is crucial to determining what the status is and how the project proceeds from this update. It needs to be as accurate as possible. If we bag it, we can force it Critical or Near Critical resulting in an erroneous shift in resources. If we only rely on the best-case scenario, we may not allow the focus necessary to recover this next update period.

The owner really needs to have someone in the field, daily, keeping up with the actual and planned progress. The rest of the schedule progress update is based on this data. Any revisions and planning done by the contractor to recover time lost or shift resources to maintain schedule are dependent on this information being accurate. Any potential delay or change order issues are also affected by this information. This information sets the status of the project at the time of the progress update. This determines the current Critical and Near Critical Path(s).

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Network Logic Progress Update Information for Owners.

As a continuation of my previous posts, I will continue to discuss some of the important progress update items we review and analyze.

I will now discuss the process of verifying the network logic is complete.

When the contractor adds the actual Start and Finish Date and expected Finish Date data to the schedule update, the new scheduled completion date if most often not what any of us want. Usually, there has been slippage in work progress in an area that must be addressed.

The contractor will investigate and add resources or increase hours for that work or re-sequence the work in the most cost-effective manner possible to recover any lost time. The contractor is usually required to convey that plan to you with the schedule update narrative. However, this is seldom the complete picture…..

Quite simply, when there are logic changes made, it is easy to create missing logic such as an activity with one successor with only a Start-to-Start, SS relationship. This leaves this logic open as the finish of the activity does not drive the start or finish of any other work.

Reverse logic can also be inadvertently created. This is when an activity has only a predecessor with a Finish-to-Finish, FF relationship and a successor with an SS relationship. With this condition, any increase in duration of this activity will actually pull the successor back in time. Not realistic…

Those are a couple of the basic items we look at.

It is simple enough to “recover” time on the update by shortening a duration here or there and perhaps changing some Finish-to-Start, FS logic to Start-to-Start, SS logic. If the contractor can actually commit to the production necessary to achieve the shorter duration, great. If the work can actually be completed with the new logic, that’s good too.

The means and methods of how the contract plans to execute the project is really only of concern to us if it is blatantly clear it is not achievable. This is only my humble opinion. We won’t delve into construction contract law in my posts. I’m not qualified.

However, the schedule specifications and schedule best practices have been developed to provide a means of maintaining a valid schedule. We can argue means and methods of the execution, but the requirements for the schedule provide us with the tools to manage the schedule update process correctly and keep a valid schedule in place each period for managing the work and potential delays and changes.

That said, we run filters and programs that provide us with the list of items changed between schedules. This lets us know what changed, but not necessarily why. This is why the schedule update narrative is important. It is the contractor’s tool to convey this information to the owner.

If we find several relationship changes to activities which were on the previous period schedule update Critical Path for Near Critical Path(s), we need to know why these logic revisions where made. Was it to better sequence the work based on input from the subcontractor’s performing the work? Is it an attempt to shift the Critical Path? Is it masking a lack of performance for work on the Critical Path? Same holds true for the Near Critical Path(s).

Often times, the contractor is able to better plan the work immediately in front of them. This involves minor revisions to the logic and/or durations. Any changes to these items and other items such as calendars and resources should be included in the schedule update narrative and explained.

It’s easy to spot the poor performance trend when you have an Owner’s scheduler review each update period. This provides an early flag for the owner and the contractor, so the necessary actions can be taken to recover sooner rather than later……

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP