Construction Scheduling. Schedule Performance Measurement, Part 2. (For Owners).

When monitoring and responding to the Contractor’s schedule performance on the project, how do you know if the schedule update is even valid for use?

When we review a schedule progress update, we need to first determine if the schedule update is a valid update. By that, I mean is the logic still complete? Have there been any revisions with this update that result in the schedule not meeting the contract requirements or best practices? It doesn’t take much to render a schedule useless….

There are most likely logic revisions, changes to lag values, or possible changes to calendars or assignments. There are also deletions and additions of activities and/or Activity Relationships. Then there are changes to quantities or Resources which may impact Activity Durations or Resource Calendars.

For this post, we will address changes to the logic.

Personally, the first schedule “quality check” I make is for complete logic. The Primavera P6 schedule log provides a basic check. But I also use third party software that provides a more in-depth check for activities which may only have an SS relationship to their only successor activity. Sometimes, the check uncovers missing lag values or “reverse logic”. It may even uncover an SF relationship. All of these must be identified and addressed.

Often, when the Contractor is making schedule revisions to recover lost time for the update period, they make subtle changes to logic. As a Project Owner or CMa, we need to understand what was revised and why. If the relationship for an activity in the current or previous period Longest Path was changed from an FS relationship to an SS relationship, with or without a lag, to pull the scheduled Finish Date back, we need to understand that.

The same applies to the previous period or current update Near Critical Path(s).

If the contractor makes a logic revision for an activity which results in the only successor activity having an SS relationship, an open end is created. (There should have been an FS or FF relationship added to complete the logic). Otherwise, the finish of the activity does not drive anything in the schedule. This is an open end, (which does not show up on the Primavera P6 schedule log).

Any “open end” relationships make the schedule network logic incomplete. Sure, there are activities that once complete will not drive any other activity or work until the project is complete, if that is the case, they should be tied to Final Completion or whatever the last activity in the schedule is called. But more likely, the activity relationship was missed during development or when making revisions.

However, if this activity is supposed to drive other work, the relationships should model this. Not having complete logic for just one activity results in an erroneous schedule network. The activity could potentially be Critical or Near-Critical, but without the complete logic, there is nothing in the schedule to model the intended sequencing of the work for the affected network path. This means the Total Float values and scheduled dates for driven successor activities on this logic path are incorrect.

One of the basic checks and the first check I make is to verify the schedule network logic is complete. As an owner’s rep, we cannot know the detailed intent of the schedule sequencing, but we can identify open ends and any questionable logic we discover.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what the performance of the actual work in the field is, compared to the planned performance. Unless we have a valid schedule update to measure with, and against, and understand the impact of acceptable schedule revisions, we cannot provide an accurate measurement.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Schedule Performance Measurement, Part 1. (For Owners).

Are you responsible for monitoring and responding to the Contractor’s schedule performance on the project?

Do you review each schedule update and compare dates in the new update with the dates in the baseline schedule?

Do you compare the Milestone Activity dates to the baseline schedule?

There are many different methods of analyzing project schedule performance.

When we review a schedule progress update, we need to first determine if the schedule update is a valid update. By that, I mean is the logic still complete? Have there been any revisions with this update that result in the schedule not meeting the contract requirements or best practices? It doesn’t take much to render a schedule useless….

There are most likely logic revisions, changes to lag values, or possible changes to calendars or calendar assignments. There are also deletions and additions of activities and/or Activity Relationships. Then there are changes to quantities or Resources which may impact Activity Durations or Resource Calendars, depending on the schedule settings selected.

This should all be addressed in a manner that conveys the actual revisions with the reasons for the revisions as part of the schedule update narrative the Contractor submits with the schedule update. Unfortunately, this is rare. Typically, we see the “digger” report with a general comment addressing the high-level view of the update.

Not really helpful for our use.

So, we plow ahead with the intent to complete our review of the schedule update for this period.

First, we need to complete several “quality checks” of the schedule to validate it for use.

In my next post, I will walk through some of the more common items we check for.

Until then, be suspect of schedule updates without, or with vague schedule update narratives. There is much that can be changed in the program, that will not be transparent to the owner without a thorough review and analysis of the file by an experienced schedule professional.

As  Planning and Schedule Professionals, we need to provide the Project Team with the “tools” they need to manage the project. The owner needs to know what the performance of the actual work in the field is, compared to the planned performance. Unless we have a valid schedule update to measure with, and against, and understand the impact of acceptable schedule revisions, we cannot provide any accurate performance measurement.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Is the Schedule a Complete Schedule? (For Owners).

Do you review your Baseline Schedule to make sure all the work to complete “The Project” is included?

Are you sure?

When the contractor develops the schedule, they should be planning the project execution first. This includes the phasing of the project, the necessary permits, the long lead submittals, the procurement of subcontractors, equipment, and material, the close-out of the project, and the actual work necessary to build the project.

Often, we see schedules which do not include permits, or the procurement of long lead items, or complete commissioning, testing, and inspections. Let’s not forget the closeout requirements for as-built documents, warranties, or training, (if required).

The CPM schedule should include all the work necessary to execute the project.  An easy way to ensure all the work is included is to make a list of all the closeout deliverables and compare that to the WBS for closeout section of the schedule. The same for special inspections, commissioning. For whatever reason, we always look closely at the construction section of the schedule, but tend to gloss over the administrative, procurement, and commissioning sections.

Just as we look at constructability for the project plans, we need to thoroughly look at the project schedule to make sure all of the deliverables are included. And, the activities to provide these deliverables need to be complete and broken down into sufficient detail to control the work!

An activity at the end of the project schedule that says “Finish Project” is of no use. All the activities necessary to actually plan and control the post “Substantial Completion” work for the project should be as detailed as the construction work is. The same for the commissioning and testing of systems.

And, let’s not forget the initial administrative requirements which have to be fulfilled prior to starting any work. We usually need an approved Safety Plan, an approved environmental permit, and building permit at a minimum. The time to develop these, get them submitted and reviewed and approved needs to be in the front of the schedule.

Also, we need the long lead time equipment or material submittals in the schedule. I also like to have the main materials submittals, in general form, in the schedule just to make sure we get them in and reviewed in time for their use in the project. Often, the contract documents state the required review period for the owner. We use this for the review period in the schedule.

There should be a fabrication and delivery activity(s) for any major equipment which should drive the start of any installation of the equipment. This activity(s) should be driven by the submittal and procurement of the equipment. Often, this will drive the Critical path.

Everyone tends to really look at the construction activities. As  Planning and Schedule Professionals, we need to look at the project deliverable as a whole.

I’m sure many of you have comments or additional insight into this subject. Please share!

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP