Construction Scheduling. Don’t let the Near Critical path Sneak up on Your Project!

SurpriseDo you diligently keep track of the work on your project’s critical path?

How we define the critical path is a topic for another time. For now, let’s just focus on what we are tracking as critical based on total float values, which do tie into the longest path definition with variances for calendars…..

How often has the critical path for your project shifted during the project duration? Do you show as much diligence with tracking the near critical activities as you do the critical path activities?

You should, and I’m betting that you do. But, sometimes, it still sneaks up on us!

I prefer to keep my eye on both. And then I usually only focus on the nearest couple of near critical paths. 80/20 rule….. By staying aware of the calendars assigned to the activities on my near critical path(s) and looking at the trend for slippage for these activities, I generally find I realize the pending in time to intervene. I like that much better than after the fact, but I’d like to deal with the pending impact sooner, as I’m sure we all would.

I do this by comparing the past near critical path activities to the current activities to look for slippage in my layout and filter. This helps. I also like to track the schedule slippage of the activities with a total float value lower than a specific total float value dependent on the schedule status. I find it easier to spot the start of the trend and make a note to track that activity next update. I then look at the drivers to see what is causing the slippage. Pretty simple. There are more elaborate methods of analysis for determining trends and slippage and identifying potential impacts, but I like to start with the simple methods to get an immediate fix on the schedule status.

There are always “exceptions to the rule”, but this is one I try to follow.

What other methods have you found to successfully identify the near critical path negative trend?

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. The problem with Start to Start Relationships. Or, Why doesn’t a Delay to this Activity Duration push my Finish Date?

person-question-300x300Do you regularly use Start-to-Start SS relationships? Perhaps you add a lag to drive the start of the successor out a few days?

Have you had problems with this practice? Perhaps a delay to the completion of the predecessor activity is actualized, but does not impact the schedule?

This is a common practice, unfortunately. The best practice is to add an additional successor with a Finish-to-Start FS relationship, or even a Finish-to-Finish FF relationship. This will provide the logic that allows the delay to the completion of the activity to drive other work. Without that additional successor activity, what you have is an “open end” and the activity finish does drive any successive work. It could never complete and you would not see the problem in the logic.

This condition is simple to prevent. Just make it a practice to always add a FS or FF successor when using a SS relationship. The problem usually happens when you’re trying to recover time and start to schedule work concurrently. You simply forget to add the additional successor….

Personally, I like to develop my schedules with all FS relationships unless the plan actually calls for a SS condition. If I have the need to use SS relationships, I assume my work isn’t broken down into enough detail to allow me to sequence the work logically.

There are always “exceptions to the rule”, but this is one I try to follow.

What other methods have you found to successfully utilize SS relationships, with or without lags?

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. How do we, as Schedule Consultants, “Value” our Services?

QuestionDo you provide proposals to contractors or owners for your schedule development and management services? Do you provide a lump sum hard bid based on the project? Or, do you provide an hourly rate for your services? Which is best? Are there circumstances that make one the better choice?

I still struggle with this issue.

At some point, all of us are asked to propose on a project.

So, what do you do? What do you use as your guide for setting a lump sum price proposal?  Do you estimate your hours based on past, similar projects? How do you account for relying on a new project team for input and reviews?

Do you provide an hourly billable rate? How does your client budget for you services? Do you provide a budget estimate of hours and your rate for their use?

I typically provide a budget estimate based on my estimated hours and billable rate. But even then, coming up with the hours for a new client and team, and hoping for proactive input for development and updates/revisions is very subjective. But I do my best to provide a budget estimate they can have confidence in.

There must be a better way to go about pricing our work based on the value we bring to the project.

What works for you? Have you figured out a “safer” way to price the project scheduling services you will provide?

I believe that we, as planning and scheduling professional consultants, should strive to provide the best possible schedule support to assist the project team with providing a successful project.

The question is: As consultants, how do we “value” this?

We must always maintain our integrity and be honest with our client.

What has your experience been?

Real scheduling is messy. But we all deal with issues all the time…..

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Spotting a Potential Resource Issue Early. Or, Why isn’t my Contractor Keeping up?

QuestionWould you like to be able to spot a potential contractor or subcontractor production shortfall early? Perhaps get ahead of the lagging work?

There are many ways to mine this info and establish the trend. I’ll offer a very simple method for P6 here.

If you set the percent complete type to physical, display the physical percent complete and the duration percent complete columns along with the start and finish date columns, you can spot potential production issues quickly when you update.

Personally, I like to run my cost based on my physical percent complete, but different project types require different methods….. But for this method, we will be basing the cost complete on the physical percent complete prorated over the entire duration.

Once you have the actual start date and physical percent complete you should enter the expected finish date to establish the revised scheduled finish date for the activity. Doing this will result in a different duration percent complete than the physical percent complete you entered based on actual work completed. The variance will show if the production rate for this work was accurate as actualized to date or if the actual production rate is better or worse than planned.

If the work is 50% physical complete and the adjustment to the scheduled finish date forces the duration percent complete to be 65%, you may want to investigate to find out if the original assumptions were incorrect or if this resource is adequate to meet the production as planned. If the same resource is having problems for several activities, there could be a trend that needs attention.

Simple. There are more accurate ways to measure this, such as resource man hours or units completed. But this is a quick, easy way to spot an issue just by looking at the schedule as you update or look over the schedule in a meeting…..

What other “easy” ways have you found to monitor the work and spot potential production issues?

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Why are there no schedule requirements in the RFP?

person-question-300x300Are you ever asked to develop the project baseline schedule and find out there are not any requirements for the schedule in the contract documents. It could happen…..

Or the requirements are “fuzzy” at best or so limited as to be of little value.

At some point, all of us have come across this scenario, or soon will.

So, what do you do? What do you use as your guide for setting the critical path, activity and duration types, and resource and cost loading? Does your company have guidelines for this situation? Do you have a preferred method you fall back on in these situations?

I have a couple of guidelines based on useful schedule specifications I’ve worked with in the past. But I have to find out what the project team wants from the schedule before I can decide which requirements to employ.

Does your client want to project and track progress using resources? Does the owner? Does your client want to use cost loading? If so, by unit cost or lump sum? What does your client expect or understand about setting the critical path? Will the project be resource driven? Or will durations and logic rule with resources handled via logic? What about constraints? Calendars and weather days?

There are many more variables we work with every day. Without schedule requirements for the project, we are left deciding which settings and approaches are best for the specific project. With experience, we can become comfortable with this situation. But what if the project is a new industry or contract type for you?

How do you approach these situations in your company?

I believe that we, as planning and scheduling professional consultants, should strive to provide the best possible schedule support to assist the project team with providing a successful project.

The question is: As consultants, how do we accomplish this?

We must always maintain our integrity and be honest with our client.

What has your experience been?

Do you just default to the simplest methods and settings?

Do you advise your client to convene a team meeting with the owner to see if they can agree on some basic requirements?

Do you just pull one of you favored specifications out of the drawer and run with that?

Real scheduling is messy. But we all deal with issues all the time…..

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP