Construction Scheduling. Developing the “Time Impact” Fragnet. Or, this is how bad this change hurts!

Avoiding Project DelaysI often assist contractors with their schedule development and updates. This also includes preparing the “fragnets” for Time Impact Analysis, (TIA) or change orders. I find that many smaller contractors are not used to following a procedure for managing their schedules. This makes it nearly impossible to manage their change order time impact.

What I find, more often than not, is a schedule, (not the latest update, if there is one) that someone has increased the duration for a piece of work that is “impacted” by the change order or delay.

This may seem intuitive to the project manager or superintendent. It may actually work somewhat to model the impact of the change order or delay impact.

But, does it model the actual change or delay? Is it applied to the most recent accepted update or revision? Can it be used as a tool to visually explain the sequence of events associated with the change or delay to arrive at an understanding and agreement of the change package, associated relationships to existing work, and impact to the scheduled completion date?

There are best practices and white papers devoted to the development of “fragnets”. As professional planning and schedule consultants, we should follow these best practices. But, we still need the involvement and direction only the contractor can provide.

The contractor needs to explain the series of events driving the impact and be prepared to provide dates and references to RFI’s, field directions, RFP’s, meeting minutes, or other records which will support the request. We can then build the model of the impact events accurately. Then the contractor needs to tell us specifically which activities this impact actually drives so we can apply the correct logic. We also need to know what work was starting or underway when the issue presented so we know how to apply that logic as well.

It is much more complicated than simply increasing the duration of the activity impacted. The goal of the professional planning and schedule consultant is to model the impact package so it can be presented to the owner as an easily understood representation of the group of events laid out in a timeline fashion with durations and logic the owner can agree to or discuss further. Once this is accomplished, there isn’t much more to argue about. The impact model or fragnet stands on its own and the subjectivity is all but removed from the issue.

But this all depends on the willingness and ability of the contractor to provide the information and direction to support the development of the fragnet.

What other methods have you found to help with this issue?

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Developing trust with the Owner, for Schedule Management.

person-question-300x300I often assist contractors with their schedule development and updates. This also includes preparing the “fragnets” for Time Impact Analysis, (TIA) or change orders. I get the impression from many owners that they do not trust the fragnet or analysis supporting the time extension request.

I worked many years on the “owner’s side” of projects. I understand the concerns most owners have. It only takes being lied to once to create a skeptic…

How do we, as professional planning and schedule consultants overcome the widespread distrust owners have, specifically when it comes to developing and supporting fragnets, TIA’s, or change orders?

I find the majority of contractors I work with to be honest & above board. They act with integrity and genuinely want to provide the best product and service they believe the owner has contracted for.

I find the majority of owners I work with believe they have provided the contractor with a good set of contract documents to work with and really do want the contractor to be successful on their project.

I believe the most important thing we can do, as professional planning and schedule consultants, is educate our clients by teaching them how the time impact “plugs” into the schedule; how the various calendars with non-work days affect the scheduled dates and total float downstream of the fragnet; how to properly manage the schedule updates and revisions to use the correct schedule to base the impact on.

If we could teach our clients the basics of change management for schedules, they might have a better understanding of what is prepared and presented, which would perhaps help in making the “negotiation” of the time impact go smoothly.

Who knows? It just might help build a little trust on the project…

What other methods have you found to help with this issue?

I’d love to hear what you think!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Please visit my “The Blue Book” ProView.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Impacts of Unrecognized Owner Delays!

Delay outputsAs construction scheduling professionals, we’ve all worked on projects which have been impacted by an owner delay which was not recognized as valid by the owner.

This happens. We have to deal with it. Some general examples that come to mind are:

  1. Unrecognized change in the owner’s program resulting in a change to the contract scope of work and design.
  2. Unrecognized unforeseen condition which changed the geotechnical design or suspended the project until remediation work could be completed.
  3. Unrecognized specification or drawing ambiguity or omission resulting in additional or changed work.
  4. Unrecognized delays for owner operations not included in the bid docs.

What types of schedule delay events have you seen? How did you, as a construction scheduling professional manage them? How did the project team manage them?

I’m interested in hearing your stories!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Paul Epperson CCM, PMP, PSP, PMI-SP

Construction Scheduling. Schedule Delays!

Expect-Delays-sign(1)We’ve all worked on projects where a major event has occurred and the project team had to scramble to manage the crisis.

This happens. As construction scheduling professionals, we have to deal with it. Some general examples that come to mind are:

  1. Very extreme weather events such as hurricanes & floods. We plan for “normal” weather and manage weather impacts in excess of the anticipated “normal”. But an extreme weather event requires the immediate involvement of the entire project team.
  2. Drastic change in the owner’s program resulting in a gross change to the contract scope of work. This could be a facility design changing from a male facility to a female facility, at 70% construction complete. There would be a lot of rework and resequencing of work required. It happens……
  3. A serious unforeseen condition which changes the geotechnical design or suspends the project until remediation work can be completed. This is not all that unusual and is typically mitigated. But, it is still a major disruption to the start of the project.

What types of schedule delay events have you seen? How did you, as a construction scheduling professional manage them? How did the project team manage them?

I’m interested in hearing your stories!

Please visit https://conschmanservices.com to learn more about Construction and Schedule Management Services, LLC

Please visit my LinkedIn account to learn more about me.

Paul Epperson CCM, PMP, PSP, PMI-SP